SWAN OFFICE PARK

Project outline and scope of works

Aquarius Grup’s appointment for Swan Office Park was initially to provide the lender, with a project surveyor for the duration of the construction activities.

The scope of Aquarius’ work was to review of all of the construction contracts, design documents, project schedule and the other critical components of the project and report on their completeness. Aquarius also provided support in review of commercial relations and communication between the contractor and the developer, cost/budget over site, including monitoring of expenditures, including all soft costs. We also ensured that the ‘’work in place’’ claimed in the contractor’s disbursement requests was consistent with the conditions in the field. The project was concluded with a comprehensive closing review and report which included a review of the technical book and as built design information, which ensured the project was successfully completed and signed off.

Aquarius was also appointed, by separate agreement, to carry out a Post Construction BREEAM assessment under the 2009 version of BREEAM International: Offices. After providing expert BREEAM guidance and the completion of the assessment report, Swan Office Park became the first office building in Romania certified under BREEAM International: Offices 2009 scheme.

Project Data

TYPE: Office Development

SIZE: Phase 1 - 59 000 m2

NO. OF BUILDINGS: 3 buildings

CONSTRUCTION TIME: 39 months

NO. OF CONTRACTORS: 3 General Contractors

SERVICES PROVIDED: Lender supervision reporting, budget forecast, reconciliation and BREEAM Certification in the Post Construction phase using BREEAM 2009 scheme

FORM OF CONTRACT: Lump Sum with Variations

DESIGNED BY: Client and Contractor